DHL Supply Chain: ASRS Fire Protection
Memphis, TN

Category: Material Handling/Warehouse

Carine’s fire protection team developed an alternative design request and obtained fire department approval for protection systems necessary to obtain beneficial use of the top-loading automated storage and retrieval system (ASRS) in a new 500,000 square foot distribution facility. The fire department issued a corrective-action notice weeks prior to facility opening. Following approval, Carine’s project management team oversaw contractor buyouts, design and submittal review and approval, installation, testing, and obtained the certificate of occupancy in record time. Carine’s solution mitigated significant operational disruption for DHL and its customers.

Related Projects

Puma: Distribution Center
Torrance, CA


Niagara Bottling Company: SmartStore Installation
Rialto, CA


Comprehensive
Project Management
Solutions

Enter your email address to receive notifications of new posts straight to your inbox.
Something went wrong. Please check your entries and try again.
building-design-high-tech